Client Name: Alex Corporation
Commencement Date: 16 October 2015
Completion Date: 15 February 2020
The project includes design, engineering, manufacturing, test delivery, installation, completion and commissioning of 230kV overhead line bays in the existing Stung Hav Substation, the 50km line-twin-TACSR transmission line from Stung Hav to Chamkarloung, the 140km line-ACSR Curlew transmission line from Chamkarloung to Bek Chan.