Client: Tenaga Nasional Berhad
Completion: October 2019

This project includes design, engineering, supply, erect and commissioning of 500/275kV AIS (2 x 1050MVA) complete with Auto Transformers, 275kV underground cable connection, 500kV switchgears, 275kV switchgears, 275kV OHL connection, protection, telecontrol and all associated civil works. 

The detail scope of works consists of:

1) 500kV System

2) 275kV System

3) Secondary Equipment for 500kV and 275kV System

4) Telecontrol Equipment

5) Civil

6) Competent, testing, safety, insurance, dismantling, CIDB