Commencement Date: 15 April 2021
Client Name: National Grid Corporation of The Philippines (NGCP)
Location: Philippines
The project includes construction of the Caticlan cable terminal station (CTS)–Boracay line, which will comprise a 2-km-long, 138 kV single-circuit submarine cable, an 8-km-long, 138 kV single-circuit underground cable and a 1-km-long, 69 kV single-circuit underground cable. In addition, the project includes construction of the 14-km-long, 138 kV Nabas–Caticlan overhead line, the 138/69 kV Boracay substation and expansion of the existing 138/69 kV Nabas substation. The project will help to reinforce electricity transmission services in Aklan province, which is currently being served through the 69 kV Nabas–Caticlan–Boracay overhead line and submarine cable system.