Power Generation & Rail/ Track/Infrastructure
Year | Client | Description | Country | Substation Name |
---|---|---|---|---|
2019 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Supply, Engineering, Testing, Installation and Commissioning of New Governor Control System inclusive of:
|
Malaysia | Gantisan, Sandakan |
2019 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Supply, Engineering, Testing, Installation and Commissioning of New HMI System for Plant Control System, inclusive of Integration with Existing Unit Control System, Excitation System, Protection System and RTU System. |
Malaysia | Tenom Pangi, Sabah |
2019 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Supply, Design, Installation, Testing and Commissioning of New Control System, Turbine Governor System and Auxiliaries System inclusive of:
|
Malaysia | Kenyir, Cameron Highlands and Sungai Piah Power Stations |
2018 | Pembinaan Indah P.I.E Sdn Bhd | Relocation of GE Gas Turbine GTM LM2500 from Melawa to Batu Sapi Power Plant. |
Malaysia | Batu Sapi, Sabah |
2017 | Malakoff Berhad | Complete Upgrade of Existing GT HMI Hardware, inclusive of Supply, Design, Engineering, Installation, Testing and Commissioning. |
Malaysia | Lumut Power Station |
2016 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Turbine Control & Governor Electrical System inclusive of:
|
Malaysia | Melawa, Sabah |
2016 | Malakoff Berhad | Establishment of Power Plant Generator Excitation System at Lumut. |
Malaysia | Lumut, Perak |
2016 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Upgrading of DCS for CCP Boiler, Steam Turbine and GT Interface Using Latest Control System from Valmet DNA DCS System, inclusive of Project Management, Supply, Design, Engineering, Assembly, Testing, Installation and Commissioning. |
Malaysia | Patau-Patau, Labuan |
2015 | Sarawak Energy Berhad | Plant Information Management System. |
Malaysia | Sejingkat, Sarawak |
2015 | TNB Repair and Maintenance Sdn. Bhd. (REMACO) | Complete Hydro Turbine Control inclusive of:
|
Malaysia | Tenom Pangi, Sabah |
Year | Client | Description | Country | Substation Name |
---|---|---|---|---|
2022 | MMC Gamuda KVMRT (PDP SSP) Sdn Bhd | MRT2 Metro Project Engineering, Procurement, Construction, Testing & Commissioning of Power Supply and Distribution System. |
Malaysia | Sg Buloh - Putrajaya |
2021 | SIPP – YTL JV | Turnkey Contract for Design and Build for Electrification Works Package including OCS and TPS for 200km Gemas to Johor Bahru, Malaysia. |
Malaysia | Gemas – Johor Bahru |
2019 | Xenix Electech Ltd | To Install OCS System and Components for Redline Project including Machinery for Sector Bang Sue to Rangsit. |
Thailand | Bangkok |
2019 | Dhaya Maju Infrastructure (Asia) Sdn Bhd | Design, Construction, Completion, Testing, Commissioning and Maintenance of the Systems Works (excluding TETRA). |
Malaysia | Rawang-Seremban-Batu Caves- Port Klang |
2017 | Keretapi Tanah Melayu Berhad (KTMB) | Repair Works for Damaged of Overhead Catenary System (OCS) Equipment at Segambut - Spg. Batu (UM, DM & Sentul By Pass Line) Due to Derailment of KTMB Cargo Train No.328. |
Malaysia | Kuala Lumpur |
2017 | Lion Pacific Sdn Bhd | System Works Comprising (Design and Build):
|
Malaysia | Subang Skypark |
2017 | Puncak Gali Harmoni Sdn Bhd | Re-energized, Installation, Testing & Commissioning of Overhead Line System at Platform 2 (Up Loop) Subang Jaya Station. |
Malaysia | Subang Jaya, Selangor |
2016 | Keretapi Tanah Melayu Berhad (KTMB) | Repair Works for Damaged of Overhead Catenary System (OCS) Equipment Due to Derailment of KTMB Goods Train No.344 at Batu Gajah on 28.10.2016. |
Malaysia | Batu Gajah, Perak |